Don Mario Upper Mineralized Zone (UMZ)

In May 2009 the Board approved development of the Don Mario UMZ, following completion of a detailed operational study that incorporates a feasibility summary based on an updated mine model. The UMZ mine plan contemplates a flotation plant with a mill throughput of 1,900 tonnes per day over a nine year mine life. The goal is to achieve production towards the end of fiscal 2010.

Based on the 2006 pre-feasibility report dated December 19, 2008, Kappes, Cassiday & Associates completed a detailed operational report, which report was updated on May 15, 2009. Economics were favorable using conservative forecasts of metal prices, but for a flotation-only scenario. The modified mine plan requires stripping and stockpiling the Porous and Oxide Zone mineralization and mining and processing the Transition and Sulphide Zone mineralization in the early years. The stockpiled oxide and porous mineralization will then be floated to recover the gold and silver in the later years. During the study, 31 holes were drilled within the pit design to collect samples for further metallurgical testing. AMEC (Peru) S.A. completed a National Instrument 43-101 compliant resource estimation of UMZ mineralization that included these 31 drill holes. This resource estimate supercedes the 2006 resource estimate used for the detailed operational study.

Further studies showed that the project economics greatly improve when a leach-precipitation-flotation process is applied to the porous, oxide, and transition zones.  This scenario not only eliminates the need to stockpile the porous and oxide mineralization, but allows for the beneficiation of the copper oxides thus increasing the life-of-mine copper production by approximately 40,000 tonnes

Mineral Resource Estimate Effective December 19, 2008

Zone Classification ’000 Tonnes Cu (%) Au (g/t) Ag (g/t) AuEq, (g/t)
Porous Indicated 539 1.99 1.39 43.4 7.30
  Inferred 45 2.54 1.44 29.3 8.52
Oxide Indicated 1,7888 1.74 1.63 50.7 7.03
  Inferred 173 1.74 1.43 43.8 6.72
Transition Measured 913 1.32 1.45 51.7 5.78
  Indicated 1,041 1.23 1.33 46.6 5.35
  Inferred 82 1.08 0.95 45.1 4.56
Sulfide Measured 774 1.19 1.18 32.3 4.82
  Indicated 1,148 1.11 1.05 33.5 4.53
  Inferred 17 0.78 0.95 18.20 3.29
Total M&I 6,203 1.43 1.37 44.0 5.85

Although metallurgical testing of the Porous and Oxide Zones shows that the gold and silver from these zones can be recovered economically, testing continues in order to improve not only the gold and silver recoveries, but the copper recoveries as well.